Guide · guides

    Part L transitional arrangements: which standard applies to your build

    The transitional rules decide whether a plot is assessed under Part L 2021 or Part L 2026. They apply building by building — and that catches people out.

    9 min readBy Nabhan Islam Reviewed by Awais Sarwar, MSc Updated 15 Sept 2026
    Part L transitional arrangements: which standard applies to your build
    The short answer

    For work that is not higher-risk building work, Part L 2021 can still be used where a building notice, initial notice or full plans application was given before 24 March 2027 and work on that building starts before 24 March 2028. The protection applies building by building, not scheme by scheme, so on a phased site some plots can sit under Part L 2021 while later plots fall under Part L 2026. For higher-risk building work, the changes do not apply where a valid building control approval application was submitted to the Building Safety Regulator before 24 September 2027 and has not been rejected.

    020 3092 8551

    Application deadline (non-HRB)

    24 March 2027

    Commencement deadline (non-HRB)

    24 March 2028

    Work must start on that building

    HRB application deadline

    24 September 2027

    Unit of assessment

    The individual building

    Awais Sarwar, founder of Part L Consultant

    Who runs your contract

    Awais Sarwar, MScAccredited Energy Assessor

    Awais is an accredited domestic and commercial energy assessor and the owner of Team EPC Ltd, which trades as Part L Consultant. He has surveyed and lodged EPCs across flats, houses, HMOs, managed portfolios and commercial premises throughout London and the Home Counties, and is currently studying an MSc in philosophy alongside running the business.

    EPC Register
    Accredited assessor
    MSc
    Built environment
    MSc Philosophy
    Currently studying
    10+ years
    London property
    Part L focus
    Design to as-built

    Off the clock: cricket, family time, an MSc in philosophy in progress and finding London's best food.

    Awais Sarwar away from work, out in a London park

    Awais Sarwar

    Founder · Accredited energy assessor

    About Awais

    The two conditions for non-higher-risk work

    The transitional arrangement for ordinary work has two limbs, and both must be satisfied for a building to stay under Part L 2021. First, a building notice, initial notice or full plans application must have been given before 24 March 2027. Second, work on that building must start before 24 March 2028. Miss either and the building is assessed against Part L 2026.

    How the non-HRB transitional test runs

    1. Before 24 March 2027

      Building notice, initial notice or full plans application given to the building control body.

    2. Before 24 March 2028

      Work starts on that specific building.

    3. Outcome

      That building can be assessed under Part L 2021.

    4. If either is missed

      That building is assessed under Part L 2026.

    Shared company experience

    Real buildings.
    Relevant experience.

    Selected work delivered by our sister companies, Team EPC and Fire Risk Specialists. Every card names the business responsible; these are not presented as Part L commissions.

    Exterior of Pinnacle Tower in Wembley, London
    Team EPC

    Wembley, London

    Pinnacle Tower

    Delivered by Team EPCBulk domestic EPC programme

    A tower-wide programme, coordinated as one instruction.

    Exterior of City Deal Estates in Central London
    Team EPC

    Central London

    City Deal Estates

    Delivered by Team EPCManaged portfolio energy assessments

    Period properties reviewed building by building.

    Exterior of 1 Harrington Gardens in South Kensington, London
    Fire Risk Specialists

    South Kensington, London

    1 Harrington Gardens

    Delivered by Fire Risk SpecialistsLuxury serviced apartments

    48 apartments. One coordinated fire risk assessment.

    Exterior of Bang Bang Oriental in Colindale, North London
    Fire Risk Specialists

    Colindale, North London

    Bang Bang Oriental

    Delivered by Fire Risk Specialists32,000 sq ft food hall

    25+ kiosks. High footfall. One rigorous assessment.

    Building by building — why phased sites are the risk

    Circular 01/2026 is explicit that the arrangement applies building by building rather than scheme by scheme. On a 40-plot site delivered in phases over three years, an application covering the whole site does not freeze the standard for the whole site: each building still has to have started before the commencement deadline. In practice that means the plots at the end of the programme are the ones to model against the newer standard, and the ones most likely to need a fabric or heating change if that has not been anticipated.

    Two ways to handle a phased site
    Modelled earlyLeft to each phase
    When the later phases are assessedAt design stage, against both standardsWhen the plots come up, often after tender
    Specification riskKnown and pricedDiscovered late, changed under pressure
    Effect on programmeNoneRedesign and re-tender of the affected plots

    Higher-risk building work

    For higher-risk building work and work to an existing higher-risk building, the relevant regulations come into force on 24 September 2027. The changes do not apply where a valid building control approval application was submitted to the regulator before that date and has not been rejected. Where protection begins with an application for one stage of higher-risk building work, it continues to later stages for as long as the original application has not been rejected or lapsed — which makes keeping that application valid a compliance issue in its own right.

    What counts as work starting

    This is the question we are asked most often, and it is the one to settle with your building control body rather than with a consultant. Building control bodies take a view on what constitutes a genuine start on a specific building, and that view is applied to the building rather than to the site as a whole. If a plot's transitional protection depends on commencement, get the position agreed and recorded in writing before the deadline, not afterwards.

    How to work out where you stand

    For a single building, the answer usually takes two minutes: check the date the application was given and the date work started or is programmed to start. For a phased scheme, it is worth tabulating the plots against the two deadlines once, at design stage, so that the standard applying to each plot is a known input rather than a late discovery. Our transition checker walks through the same logic if you want a quick sanity check before you ask us anything.

    Written by

    Nabhan Islam

    Head of Marketing & Commercial Lead

    Reviewed by

    Awais Sarwar, MSc

    Accredited Energy Assessor — Accredited domestic and commercial energy assessor, listed on the EPC Register

    9 min readLast reviewed 15 September 2026Facts verified 15 September 2026 Checked quarterly

    Sources

    1. Building Regulations circular 01/2026: Future Homes and Buildings Standard GOV.UK
    2. The Building Regulations etc. (Amendment) (England) Regulations 2026 (SI 2026/335) legislation.gov.uk
    3. Building Safety Regulator: higher-risk building work GOV.UK / HSE
    4. Approved Document L: conservation of fuel and power GOV.UK

    Was this page helpful?

    Call

    Frequently asked questions

    Last word

    Ready when you are.

    Send the drawings, get a fixed written quote, and have the design-stage calculation before work starts on site. That's the whole process.

    020 3092 8551
    Transparent pricing No obligation SAP, SBEM and EPCs England and Wales
    Awais Sarwar
    — Awais Sarwar, MSc
    MD · Accredited energy assessor
    SAP & SBEM calculations·
    Fixed written quotes
    Call